Carpet Floor Coverings
Carpet is just about the last element to install in a house flip. It has to
be after interior paint, after plumbing, after heating and air conditioning, and
after electrical trim work has been completed.
Make sure to arrange for the installers to remove the scraps. That should be
part of their contract.
If you have selected wood flooring for any of the rooms, or tile for any of
the rooms, now is the time to get on these contractors to complete their work.
Most contractors will watch a job to know when to show up. You may be
surprised to find a contractor working on your job that you did not call. That
is typical. As soon as you have a contract with the contractor, and have given a
deposit for the work, contractors will usually not need to be notified to
commence. Well, in a perfect world, they may not need to be notified. Otherwise
give them a call from time to time to make sure they are aware of the progress
of the job.
|